Client: Confidential
Anord Value: Excess of: 1 Million.
Anord Program: 22 weeks

Scope of Supply

As part of the on-going decommissioning works being carried out at a major Nuclear PowerStation in UK, the client embarked on a strategic plan to replace legacy switchgear which forms part of the critical site wide power infrastructure. Following an OJEU notice and competitive tender process, Anord were once again selected to provide 2 new dual fed Level 1 Package Substations, comprising of 4 Midel Filled Power Transformers, Busduct connected close-coupled LV Switchboards, battery charger/tripping units and electrical network protection panels to meet the project requirements. Working directly with the clients engineering team, Anord achieved all of the key project milestones on time and successfully commissioned the equipment on site in line with the client's go live dates.