Skip Navigation

Reliance St.

Reliance St.
Client: Enpure / Costain
Anord Value: Excess of: 1 million
Anord Program: 14 weeks

Scope of Supply

As part of the 631 million construction programme carried out to create a network of state-of-the-art facilities to treat Greater Manchester’s waste; Reliance Street was the first major EfW plant to be constructed and operational. As a specialist in this field, Anord were selected to provide the complete switchgear and automation package, providing large intelligent MCC's, VSD panels and the process control system. Anord and the client’s construction team worked closely to ensure that the switchgear and systems were fully tested off site, ensuring a smooth commissioning phase following equipment installation.